Update and Publish a Working IAP
To update and publish a working IAP
-
In the User view, on the main menu, click the boards icon. The Boards page opens.
-
Click the Incident Action Plan (Working) board.
-
Locate the working IAP you want to publish and, on that row, click the more icon
then select Forms List.The IAP opens. -
If needed, locate the form you want to update and, on that row, click the more icon
and select Update. -
Within in the IAP, make the necessary changes. For example, you can select or deselect objectives and forms, edit descriptions, and decide if a site safety plan is required.
-
To change the Form Status, select the Not Started, In Progress, or Complete option.
-
Click Save.
-
To approve the IAP, click Approve.
-
In an open Approver row, enter your Name, Title, Date/Time, and Approved.
-
Click the Signature field and use your browser navigation window to locate and select a file.
-
Click Save.
-
Click Publish.